How to Start an Eye Level Learning Center Franchise in 7 Steps: Checklist

Get Franchise Bundle
Get Full Bundle:
$79 $49
$99 $79
$49 $29

TOTAL:

Opening process

How does an Eye Level Learning Center go from inquiry to opening?

≈120 days Official conditional opening estimate

Daekyo America, Inc. estimates about 120 days from signing the Franchise Agreement to opening, but only when an acceptable site is already available or is found shortly after signing. The estimate is not a deadline or promise. Site and lease approval, buildout, local approvals, required training, insurance certificates, payments then due, and Daekyo America’s written standards approval all remain separate opening dependencies.

14 days Federal FDD review period Calendar days before signing or franchise-related payment.
5 days Site decision target Reasonable-efforts period after a complete proposed-site submission.
9 months Lease deadline Measured from the Franchise Agreement effective date.
1 year Opening deadline Contractual outside date, subject to stated conditions.
30 hrs/week Full-time owner role Physical presence requirement for the responsible owner role.

Data basis. Legal franchisor: Daekyo America, Inc.; parent/licensor: Daekyo Co., Ltd. The governing disclosure reviewed is the U.S. Franchise Disclosure Document issued April 8, 2026, together with its attached Franchise Agreement. Primary opening evidence comes from Items 5–12, 15–17 and 20 and Franchise Agreement Sections 1.C, 2, 4, 8 and 9. Applicable paths are a New Learning Center and acquisition of an operating Transfer Learning Center; additional units require additional Franchise Agreements. Timeline mode: official total estimate, conditional as described above. Checked July 18, 2026.

Public cross-checks: the official U.S. Eye Level franchise recruiting page, the official Eye Level U.S. corporate contact listing, and the FTC Franchise Rule resources. FDD references below are cited in plain text by year, Item, agreement section and page.

Qualifications

What must an applicant qualify for before signing?

The current official U.S. recruiting page asks prospects whether they are a U.S. citizen or Green Card holder, have at least a bachelor’s degree, have at least $60,000 in liquid capital and $130,000 in net worth, and are prepared to run and market the center and work with children. The same page says a teaching background is not necessary. These are public recruiting-stage screening criteria, not a guarantee of acceptance or a substitute for Daekyo America’s current approval standards.

The 2026 FDD adds a qualification-stage criminal background check. Daekyo America provides the applicant with FBI Form FD-258 and its procedures; the applicant must arrange fingerprinting and authorize the result to be sent to Daekyo America. The FDD says signing may be postponed if the result has not arrived. Applicants should follow Daekyo America’s current instructions and verify the submission route against the official FBI FD-258 information.

For an entity, the FDD limits ownership to three owners who reside in the state of the Learning Center and requires an equity-owning Operating Principal with operational authority; each owner signs the Guaranty and Assumption of Obligations. The entity’s governing purpose must be limited to owning and operating the Eye Level Learning Center and incidental uses. Absentee ownership is not allowed: the Operating Principal—and any 50% or greater owner who is not the Operating Principal—falls under the disclosed full-time participation rule. Source: 2026 Eye Level FDD, Item 15, pp. 48–50; Franchise Agreement §§1.C and 8.E.

Verified sequence

What is the opening roadmap for a New Learning Center?

The FDD does not prescribe a single named “application-to-award” sequence, so the roadmap below separates verified dependencies from inferred administrative order. The federal disclosure review period belongs before signing or payment; site approval belongs before lease execution; training and physical development can proceed in parallel after signing but must both clear their opening conditions.

Phase: candidate and disclosure
1

Submit the inquiry and screening information

Action: Provide the requested lead and qualification information accurately.
Actor: Applicant; Daekyo America evaluates whether to proceed.
Blocker: Failure to meet current screening or approval standards.
2

Complete qualification checks

Action: Follow Daekyo America’s fingerprint and background-check procedure and finalize ownership structure.
Actor: Applicant and background-check providers.
Blocker: Daekyo America may postpone signing until the required result is received.
3

Receive and review the FDD and agreements

Action: Review the FDD, Franchise Agreement, guaranty, state addenda and applicable exhibits.
Actor: Applicant, with independent professional advisers as appropriate.
Timing: At least 14 calendar days before signing a binding agreement or making a franchise-related payment.
Phase: contract, site and premises
4

Sign the Franchise Agreement if approved

Action: Execute the agreement and entity exhibits; pay the $1,000 initial franchise fee and $3,000 Booklet Security Deposit.
Actor: Approved franchisee and Daekyo America.
Next dependency: The agreement’s Effective Date—the date Daekyo America signs—starts the nine-month lease and one-year opening clocks.
5

Obtain written site approval before signing a lease

Action: Submit the proposed site description plus a letter of intent or other evidence of favorable prospects.
Actor: Franchisee finds the site; Daekyo America approves or disapproves it.
Timing: Daekyo America uses reasonable efforts to respond within five days after receiving the written proposal.
Blocker: No approval if the site fails required criteria or lease/signage minimums.
6

Obtain lease approval and execute the lease

Action: Submit lease terms for approval before signing; include required franchisor protections; send the signed lease within seven days.
Actor: Franchisee, landlord and Daekyo America.
Timing: Sign within nine months after the Effective Date; failure can result in termination.
Phase: development, training and opening
7

Develop the center and secure third-party approvals

Action: Prepare plans, use approved architect/contractor requirements, obtain applicable permits, complete buildout, install approved assets and systems, and stock opening materials.
Actor: Franchisee, landlord, contractor, suppliers and government authorities.
Blocker: Construction, delivery, inspections, permits and local requirements can extend the 120-day estimate.
8

Complete training and the pre-opening Business Plan

Action: Complete Self-Directed Learning, New Franchisee Training and required post-training modules; submit the required Business Plan.
Actor: Franchisee or Operating Principal and required Center Director; Daekyo America trains and reviews.
Blocker: Unsatisfactory completion can prevent opening and may support termination.
9

Clear the four opening conditions

Action: Obtain written standards approval, finish required training, pay amounts then due, and deliver required insurance certificates.
Actor: Franchisee completes prerequisites; Daekyo America issues its written standards notice.
Timing: Open no later than one year after the effective date unless Daekyo America grants more time in its sole discretion for mitigating circumstances.

Sources: 2026 Eye Level FDD, Items 5, 6, 8, 9 and 11, pp. 13–14, 23, 27–44; Franchise Agreement §§2.A–2.F and 4.A. The FTC explains the federal pre-sale timing rule in its Consumer’s Guide to Buying a Franchise.

Site approval

How are site approval, lease approval and buildout kept separate?

Site approval is not lease approval or territory protection. Written site approval is required before the franchisee signs a lease or other site document. The location must support exterior signage, have a lease term of at least three years and contain at least 600 square feet; the FDD says a typical center is roughly 900 to 1,200 square feet. Retail space such as a strip mall or town center is the default unless Daekyo America grants a written exception.

Daekyo America then separately reviews the lease before execution; the franchisee sends a signed copy within seven days. A discretionary temporary location may be allowed for up to 12 months after documented good-faith efforts to find permanent space. For buildout, the franchisee prepares compliant plans and uses approved architect/contractor requirements; Daekyo America reviews design compliance, not legal compliance. Applicable local permits and licenses remain the franchisee’s responsibility and vary by location, as the U.S. Small Business Administration explains.

SITE APPROVAL IS NOT TERRITORY PROTECTION

The 2026 FDD and Franchise Agreement state that an Eye Level Learning Center receives no protected or exclusive territory. An approved Premises determines where that center may operate; it does not prevent Daekyo America from operating or franchising other centers or using other distribution channels. Source: 2026 Eye Level FDD, Item 12, pp. 44–45; Franchise Agreement §1.E.

Training

What training must be completed before the center can open?

For a first Eye Level Learning Center, the franchisee or Operating Principal and any separate Center Director must satisfactorily complete pre-opening training. The Franchise Agreement makes New Franchisee Training virtual/online by default but allows Daekyo America to choose in-person delivery. Self-Directed Learning Part 1 precedes training, and Part 2 must be completed before opening; prerequisite self-study is due at least one week before training begins. A pre-opening Business Plan is also required, but Daekyo America’s review does not endorse its projections. Up to two days of Opening Day Support is assistance, not opening authorization.

Disclosed training and opening-support hours

Compatible hour ranges from the 2026 FDD training program; these periods are not added into the 120-day opening estimate because activities may occur at different stages or overlap with site development.

0 10 20 30 40 50 hours Franchise Orientation Day 4–6 Self-Directed Learning, Part 1 32–50 New Franchisee Training 12–15 Self-Directed Learning, Part 2 10–12 Opening Day Support 12–16

Interpretation: the largest disclosed pre-opening training block is the 32–50 hours of Self-Directed Learning Part 1; physical-center development remains a separate workstream.

Source: 2026 Eye Level FDD, Item 11 training chart, pp. 40–43; Franchise Agreement §4.A. “Opening Day Support” is on-the-job assistance at the local center or another location designated by Daekyo America.

Responsibility map

Who controls the dependencies that can delay opening?

The 120-day estimate spans multiple control points. Daekyo America controls franchise, site and lease review, training standards and its written opening notice. The franchisee controls timely submissions, site search, financing, buildout, required purchases, insurance and staffing. Landlords, contractors, suppliers, insurers and authorities control separate dependencies that Daekyo America does not guarantee.

Applicant / franchisee

Provide accurate application and qualification information.
Find the site; submit site and lease materials before commitments.
Manage plans, financing, buildout, permits, systems and opening inventory.
Complete training, Business Plan, insurance and opening-readiness tasks.

Daekyo America, Inc.

Evaluate candidate qualification and required background-check results.
Review proposed site, lease terms and design compliance.
Provide required training and identified pre-opening assistance.
Issue written notice when the center meets franchise standards.

Third parties

Landlord: acceptable lease and required franchisor provisions.
Architect / contractor: compliant plans, construction and project insurance.
Authorities: applicable permits, licenses and inspections.
Insurer / suppliers: required certificates, equipment and delivery timing.

Sources: 2026 Eye Level FDD, Items 8 and 11, pp. 27–44; Franchise Agreement §§2.C, 2.F and 8.F.

Opening readiness

What must be complete before Daekyo America allows the center to open?

The contractual opening gate has four express conditions: Daekyo America must notify the franchisee in writing that the Learning Center meets its standards and specifications; the required franchisee or Operating Principal and Center Director must satisfactorily complete training; amounts then due must be paid; and required insurance certificates must be delivered. Construction completion alone does not satisfy these conditions, and training completion alone does not create opening authorization.

Before that final gate, the franchisee also needs approved premises, required Operating Assets and Instructional Materials, designated computer systems, applicable licenses and permits, and EFT authorization. Insurance includes the disclosed $1 million per-occurrence/$2 million aggregate general-liability limits, cyber coverage, required additional-insured endorsement, and—during buildout—specified contractor/project coverage including Builder’s Risk. The opening process also includes the assigned microsite, Google Business Profile and required background checks for assistants age 18 or older.

Franchise Agreement §9.A also ties marketing to the opening period: it requires a $4,000 center-opening advertising spend under Daekyo America’s guidelines, although New Centers in Arizona, Florida, Oregon and Nevada are excluded from that contractual spend requirement. Pre-opening marketing counts only if Daekyo America elects to treat it that way.

Approved site and franchisor-approved lease are in place.
Signed lease copy was delivered within seven days of execution.
Final plans were approved before construction and required buildout is complete.
Applicable local permits, licenses and inspections have been cleared.
Required insurance policies and certificates have been delivered.
Operating assets, Instructional Materials, systems and opening inventory are ready.
Required trainees completed pre-opening training satisfactorily.
The pre-opening Business Plan has been completed for Daekyo America’s review.
EFT authorization and amounts then due are resolved.
Written notice confirms the Learning Center meets franchise standards.
Alternative paths

How does a Transfer Learning Center or an additional unit differ?

A Transfer Learning Center follows a different path. The incoming buyer must qualify, sign the Transfer Training Agreement and complete required training before takeover; the lease must be transferable, current franchise documents must be executed as required, and center deficiencies may need correction or scheduled upgrades. The seller and transferee must work together at the center for at least one month before and one month after transfer.

For additional units, Item 22 lists no Development Agreement or Area Development Agreement, and the standard Franchise Agreement grants no right to another center. Each additional center requires another Franchise Agreement. Item 5 says a qualified multi-unit franchisee pays the separate initial franchisefee for each additional agreement when the first Franchise Agreement is signed, so approvals and opening clocks should be verified unit by unit.

New Learning Center

Primary path: sign the Franchise Agreement, secure approved premises, develop the center, complete training and clear written opening approval.

Key clocks: lease within 9 months; open within 1 year.

Transfer Learning Center

Acquisition path: buyer qualification and training precede takeover; lease transfer, current franchise documents and center-condition requirements apply.

The center must be operating to transfer under the agreement.

Additional units

No area-development right is disclosed in the standard agreement. Each additional Eye Level Learning Center requires an additional Franchise Agreement.

Verify approvals and deadlines unit by unit.

Sources: 2026 Eye Level FDD, Items 5, 12, 17 and 22; Franchise Agreement §§4.A and 12.C.

Buyer verification

What should a prospective franchisee verify before committing?

Reconcile current recruiting statements with the April 8, 2026 FDD and attached Franchise Agreement, including qualification thresholds, fees, training format and state addenda. Confirm that the ownership structure satisfies the Operating Principal, guaranty, owner-count, same-state residence and participation rules. Do not sign a lease until Daekyo America has approved the site and lease terms in the required sequence.

Verify the exact Effective Date, training availability, complete-site-submission requirements, approved architect/contractor standards and evidence needed for the final written standards notice. Check local permit and inspection lead times with the relevant authorities rather than treating the 120-day estimate as a local construction schedule.

Item 20 provides current and former franchisee contacts, which can help test actual site-search, lease-review, buildout, training and authorization timing. The FTC’s Franchise Fundamentals guidance explains FDD due diligence.

Final synthesis

What is the verified opening path in one view?

The verified New Learning Center path is qualification and background review, federal FDD review, Franchise Agreement execution, written site approval, separate lease approval, development, training and Business Plan completion, then Daekyo America’s four opening conditions. The FDD gives an official conditional estimate of about 120 days from signing when a site is ready or found quickly, while separately requiring a lease within nine months and opening within one year.

The main applicant-controlled dependency is securing and developing an acceptable site on time. The main external dependency is the chain of Daekyo America reviews plus landlord, contractor, permit, insurance and delivery timing. Verify the market-specific site-and-buildout schedule before signing because time beyond the one-year deadline is discretionary, not automatic.