How to Start a Trademark Hotel Collection Franchise in 7 Steps: Checklist

Get Franchise Bundle
Get Full Bundle:
$79 $49
$99 $79
$49 $29

TOTAL:

OPENING PATH

How does opening a Trademark Collection by Wyndham hotel work?

90 days / 30 months
Official format-specific windows

There is no single brand-wide opening duration. Under the 2026 FDD, a conversion generally must finish its pre-opening phase within 90 days after the Membership Agreement becomes effective unless the attached Property Improvement Plan sets another date. A new-construction hotel must complete construction, deliver the required certification, and receive written opening authorization within 30 months. Transfers follow a separate path and may open on the effective date unless closure for improvements is required.

Data basis: TMH Worldwide, LLC is the U.S. franchisor identified in the Franchise Disclosure Document issued March 31, 2026. This article covers new construction, conversion of an existing hotel, and transfer/acquisition of an existing Trademark Collection by Wyndham facility. Timeline evidence mode: Mode A - official format-specific contractual windows, not one universal estimate. Primary evidence: FDD Items 1, 5-12, 15-17 and 20; Exhibit C-1 Membership Agreement, Guaranty and Schedule D addenda; Exhibit C-2 Master Information Technology Agreement. Checked July 17, 2026.
14 days
Federal disclosure period
Calendar days before a binding agreement or payment request.
30-60 days
Typical application review
After a completed application and supporting documents are received.
90 days
Conversion default window
Pre-opening improvements unless the PIP states another deadline.
30 months
New-build opening deadline
Construction, certification and written opening approval from effective date.
10 days
Plan-review allowance
Allow this period each time plans are submitted for review.
APPLICATION

What must an applicant submit and qualify for?

Formal candidacy uses a Membership Application describing the proposed hotel and location. The 2026 FDD requires a $2,500 non-refundable Application Fee when the application is submitted; if TMH Worldwide approves the application, that amount is credited toward the Affiliation Fee. The FDD does not publish a universal minimum net worth, liquidity threshold, credit-score floor, education requirement, or hotel-ownership requirement for every Trademark Collection applicant.

Approval is still discretionary. TMH Worldwide may require a positive market feasibility study from an approved nationally prominent accounting or consulting firm as a condition of site approval. The franchisor states that it typically reviews the completed application, supporting documents, and proposed site and awards or declines the franchise within 30 to 60 days, but it sets no contractual deadline for completing that review.

Two separate optional support programs appear in the FDD: Women Own the Room, for qualifying majority women-owned members, and BOLD, for qualifying majority Black-owned members. Eligibility and benefits are determined by Wyndham in its discretion, and the programs do not replace the core application, agreement, site, improvement, technology, training or opening-authorization requirements described here.

Personal day-to-day operation is not mandatory. If the owner does not directly manage the hotel, the member must employ a management company or individual manager with significant training and experience managing similar lodging facilities, and the general manager must complete Wyndham's required training. TMH Worldwide may require an approved third-party manager when the owner lacks significant hotel-management experience or receives a Development Incentive. Entity owners and other significant owners generally must sign the Guaranty; applicable spouses may also have signing obligations.

Buyer verification

The FDD gives process requirements but no universal published financial qualification threshold. Ask the development team which ownership, liquidity, experience, management-company, feasibility-study, and guaranty criteria will be applied to the specific applicant and project before treating preliminary discussions as approval. Item 20 and Exhibits E-1 and E-2 also provide current and former member contacts that can be used to verify how application review, PIP work, systems onboarding and opening support worked in practice.

SIGNING SEQUENCE

When do the FDD review, approval, signing, and payment steps occur?

The federal Franchise Rule requires the franchisor to furnish the FDD at least 14 calendar days before asking a prospective franchisee to sign a binding franchise agreement or pay money to the franchisor or an affiliate. That disclosure period is a pre-sale protection, not an estimate of how long application review or hotel development will take. The FTC also advises prospects to read all 23 FDD Items and seek explanations before investing.

The Trademark Collection FDD requires an application fee with the Membership Application and an Affiliation Fee when the Membership Agreement is signed for a new construction or conversion facility. Because disclosure timing and the application-payment trigger are separate rules, the buyer should verify the actual FDD delivery date and payment request sequence for the transaction rather than assume inquiry, application, approval, signing, and payment happen together.

Once approved and ready to contract, the governing document is the Membership Agreement, supplemented by the applicable Schedule D addendum for conversion, new construction, or transfer. Depending on the project, the buyer also may need the Guaranty, Affiliation Fee Note, Development Incentive Note, Master Information Technology Agreement and PMS schedule, Elavon Hosted Services Agreement, and other ancillary documents. A transfer is not merely a new conversion: the transferee assumes unresolved obligations of the prior member unless the new agreement expressly supersedes them.

1

Start the inquiry and receive the current FDD

Action: Identify the contemplated hotel, site and format, then obtain and review the current disclosure package.
Actor: Applicant and franchisor.
Timing: The FDD must be furnished at least 14 calendar days before a binding agreement or payment to the franchisor or affiliate.
Next dependency: Disclosure review does not itself constitute application approval.
2

Submit the Membership Application and proposed site

Action: Complete the application, provide supporting documents and pay the Application Fee when due, with the federal disclosure timing for that payment satisfied.
Actor: Applicant; TMH Worldwide evaluates the application and site.
Timing: Typical review is 30-60 days after a completed application and supporting documents are received.
Blocker: Feasibility-study request, incomplete documentation, unacceptable site, or denial.
3

Sign the Membership Agreement and project documents

Action: Execute the Membership Agreement, applicable Schedule D, guaranties and required ancillary agreements.
Actor: Franchisee, significant owners and franchisor.
Timing: After approval and required disclosure period.
Next dependency: The Effective Date starts key improvement and development deadlines.
4

Secure control of the location and follow the correct Schedule D path

Action: Prove ownership or qualifying lease/ground-lease control and satisfy format-specific milestones.
Actor: Franchisee and landlord or seller where applicable.
Timing: Conversion: generally within 30 days; new construction: within 90 days; transfer: by Opening Date.
Blocker: Failure to secure control can put the contractual schedule at risk.
5

Complete PIP work or new-build design and construction

Action: Follow the PIP or Approved Plans, obtain permits, maintain required construction insurance and submit requested progress information.
Actor: Franchisee, architect, contractor and government authorities; franchisor reviews for System Standards.
Timing: Conversion normally 90 days unless PIP differs; new build follows 180-day, 9-month, 18-month and 30-month milestones.
Blocker: Permit timing, plan revisions, failed inspections or missed milestones.
6

Install required systems and prepare the operating team

Action: Select an approved PMS, execute the MITA and related schedules, arrange Wyndham Gateway, approved-source purchases, photography and required training.
Actor: Franchisee, approved suppliers, technology providers and Wyndham teams.
Timing: PMS setup fees are due at least 30 days before Opening Date; training timing varies by program.
Blocker: Technology readiness, supplier lead times or incomplete required training.
7

Pass readiness checks and receive opening authorization

Action: Complete required improvements, inspections and certifications; new builds must submit the required ADA Certification before authorization.
Actor: Franchisee, architect or contractor, franchisor and relevant authorities.
Timing: By the applicable PIP or Schedule D opening deadline.
Blocker: Nonconforming work, incomplete certification or lack of written franchisor consent.
FORMAT DIFFERENCE

How do conversion, new construction, and transfer paths differ?

The same Membership Agreement framework does not create the same pre-opening sequence for every project. Schedule D separates conversion, new construction, and transfer facilities because the site-control proof, improvement work, milestones, and meaning of Opening Date differ.

Official path Key pre-opening obligation Contractual timing Opening condition
Conversion Complete PIP items designated "prior to opening"; plans may require franchisor approval. Renovation starts within 30 days; pre-opening phase generally within 90 days unless the PIP states otherwise. TMH Worldwide authorizes operation under the Marks and System.
New construction Meet milestone schedule, Approved Plans, permitting, construction, completion inspection and certification. Site control 90 days; preliminary plans 180 days; permitting/GC proof 9 months; construction starts 18 months; opening authorization by 30 months. Completion inspection, properly completed certification and franchisor authorization.
Transfer Assume unresolved prior-member obligations and complete any required PIP improvements. Renovation starts within 30 days; PIP deadline controls, otherwise 90 days. Usually Opening Date equals Effective Date unless the franchisor requires closure for pre-opening work.
Site approval is not territory protection

TMH Worldwide approves a specific hotel location when it approves the Membership Application, but the 2026 FDD says members do not receive an exclusive territory as a standard right. Any territorial protection is discretionary and must be confirmed in the governing transaction documents; site approval alone does not prevent another Trademark Collection or other Wyndham-affiliated lodging concept from competing nearby.

CRITICAL PATH

Which disclosed day-based periods can affect the opening schedule?

These durations use the same unit but have different triggers, so they should be treated as separate schedule controls rather than added together. The chart shows disclosed review periods and deadlines that a buyer can place on the project calendar once each triggering event is known.

Opening-related periods disclosed in the 2026 FDD

Scale: 0 to 90 days. The 30-60 day application review is shown as a range; other bars are fixed disclosed periods.

Plan-review allowance per submission
10 days
Federal pre-sale FDD disclosure period
14 days
Typical completed application + site review
30-60 days
Conversion renovation-start deadline
30 days
Conversion default pre-opening phase
90 days

Interpretation: The 14-day federal rule protects the pre-sale decision; it is not part of the 30-60 day franchisor review estimate or the 90-day conversion deadline. Plan review, application review, renovation and third-party permitting may overlap or occur at different stages.

Source: 2026 Trademark Collection FDD, Item 11 and Membership Agreement Schedule D; Federal Trade Commission Consumer's Guide to Buying a Franchise.

RESPONSIBILITIES

Who controls the main pre-opening dependencies?

Applicant / franchisee

Application accuracy, ownership structure, site control, financing, permits, professional advisers, contractors, construction or PIP work, insurance, staffing, required purchases, systems implementation, training attendance and timely delivery of certifications.

TMH Worldwide / Wyndham

Application and site decision, System Standards, PIP preparation for conversions and transfers, plan review, Approved Supplier information, specified integration support, inspections, training resources and the decision to authorize opening under the Marks and System.

Third parties

Landlord or seller cooperation, lender underwriting, feasibility consultant work if required, architect and contractor performance, supplier lead times, PMS and payment technology implementation, and federal, state or local permitting and approvals. These dependencies are not guaranteed by franchisor assistance.

TRAINING & SYSTEMS

What must be ready before the hotel can operate under the brand?

The franchisee must procure an approved property management system that can interface with Wyndham's Central Reservation System and execute the Master Information Technology Agreement plus the applicable PMS schedule. The current approved PMS choices disclosed in the FDD are SynXis Property Hub and Oracle OPERA. The applicable setup and implementation fee is due at least 30 days before Opening Date. The hotel also must implement required connectivity, Wyndham Gateway and the payment gateway arrangements described in the technology agreements.

Required training depends on role and format. New-construction hotels must participate in on-site Opening Training; conversion hotels may be required to do so if an architectural PIP applies. That training can occur from two weeks before Opening Date through 60 days after it and lasts from one to five days depending on room count. The initial general manager must complete the approximately 34-hour Hospitality Management Program no later than 90 days after Opening Date, while designated employees must successfully complete other required training programs.

TMH Worldwide may inspect during or after construction or renovation and may approve opening when the facility meets System Standards and the format-specific Schedule D conditions. For new construction, the member must submit the required ADA Certification before opening authorization; the architect and contractor remain responsible for professional and code compliance, and local permits or approvals remain third-party dependencies. The FDD's certification requirement should be read together with the Department of Justice's official 2010 ADA Standards for Accessible Design and advice from qualified accessibility and construction professionals.

Contractual deadline

For new construction, missing the 90-day site-control, 180-day preliminary-plan, or 9-month permitting/general-contractor milestones can shorten the construction-start deadline from 18 months to 12 months. TMH Worldwide may terminate for missed development deadlines, subject to applicable law, or may grant an extension in its sole discretion and potentially assess a $10,000 extension fee. An extension is not an automatic right.

OPENING READINESS

What should a buyer verify before treating the project as ready to open?

Use the signed Membership Agreement and its Schedule D as the project control document. The following checklist separates brand approval from the buyer's own real-estate, financing, professional, and governmental obligations.

FDD receipt date is documented and the federal 14-calendar-day pre-sale period is satisfied.
Membership Application, site information and any required feasibility study are complete.
Membership Agreement, correct Schedule D, Guaranty and required ancillary agreements are executed.
Ownership, lease or ground-lease evidence satisfies the deadline for the applicable format.
PIP or Approved Plans are current, and material deviations have written franchisor approval.
Permits, inspections, code obligations and construction insurance are handled by the responsible professionals and authorities.
Approved PMS, MITA schedules, payment gateway, connectivity and Wyndham Gateway are ready for launch.
Required suppliers, FF&E, signage, photographs and pre-opening improvements meet System Standards.
General manager, designated staff and any required opening-training participants are scheduled or completed as required.
New-construction certification is properly completed and all format-specific opening conditions are satisfied.
Any territorial protection is confirmed in writing rather than inferred from site approval.
TMH Worldwide's written authorization to open under the Marks and System has been obtained when required.
OFFICIAL SOURCES

Which public sources are useful for verifying the opening process?

The 2026 FDD and signed agreementscontrol contractual requirements. Public pages are useful for current brand context, development-process explanations and federal compliance guidance, but they do not replace the Membership Agreement or Schedule D.

SYNTHESIS

What is the verified path from inquiry to opening?

The verified path is application and site review, federal FDD review, approval and contract execution, site control, format-specific PIP or new-build milestones, required technology and training setup, inspections and certifications, and finally franchisor authorization to operate under Trademark Collection by Wyndham. The total timeline is official but format-specific: conversion pre-opening work generally uses a 90-day default window unless the PIP says otherwise, while new construction must reach authorized opening within 30 months; a transfer can follow a different opening definition.

The most important applicant-controlled dependency is keeping the real-estate, design, permitting, construction or renovation, technology, staffing and documentation work aligned to the signed Schedule D. The most important franchisor or third-party dependency is timely site/plan review and approval alongside lender, landlord, contractor, supplier and government-authority performance. Before committing to a target opening date, verify the exact Effective Date, PIP or Milestone Schedule, any discretionary extension terms, and the specific conditions TMH Worldwide will require for written opening authorization.