How to Start a SpringHill Suites Franchise in 7 Steps: Checklist

Get Franchise Bundle
Get Full Bundle:
$79 $49
$99 $79
$49 $29

TOTAL:

Opening path

What is the verified process for opening a SpringHill Suites?

No single total
Milestone-only timeline

MIF, L.L.C.’s 2026 FDD does not state one complete inquiry-to-opening duration. It instead requires a project-specific sequence: disclosure, application and approval, signed agreements, site control, financing and permits, construction or conversion, leadership and systems training, final certifications, inspection, and a signed Authority to Open. Separate deadlines are not an opening-time promise.

14 days
Federal review period

Calendar days before a binding agreement or franchise-sale payment.

15 months
Construction-start allowance

Generally measured from application approval for new development.

15 months
Start-to-open expectation

An expectation after construction begins, not a guarantee.

20 days
Inspection effort

Commercially reasonable effort after a complete ready notice.

10 days
Start notice

Notice due after qualifying construction or renovation begins.

Data basis: legal franchisor MIF, L.L.C.; ultimate parent Marriott International, Inc.; 2026 SpringHill Suites Domestic Franchise Disclosure Document, issued March 31, 2026. Primary documents: Items 1, 5–12, 15–17 and 20; Application; Term Sheet; Franchise Agreement; New Development, Conversion and Change of Ownership provisions. Timeline mode: milestone-only. Checked July 13, 2026.
1Identify the project path and request disclosure

Action: Define whether the project is new development, conversion of a non-Marriott hotel, or acquisition/relicensing of an existing SpringHill Suites.

Actor: Applicant, then MIF’s development team.

Timing: The current FDD must be furnished at least 14 calendar days before signing or payment.

Next dependency: A project-specific application package.

2Assemble the application and establish site control

Action: Submit the signed receipt, application, Forms I–IV, site materials, ownership and guarantor information, management background, project costs, projections and financing sources.

Actor: Applicant.

Timing: No universal review duration is disclosed.

Blocker: Missing legal control through ownership, leasehold or purchase contract can stop approval.

3Complete Marriott’s deal review and due diligence

Action: Respond to requests concerning the site, capital structure, owners, guarantor, hotel experience, management company and disclosed legal or financial history.

Actor: MIF approves or denies in its discretion; the applicant supplies evidence.

Blocker: Meeting a marketing profile or submitting a fee does not guarantee approval.

4Review and execute the project documents

Action: Confirm the Term Sheet, one-hotel Franchise Agreement, applicable Exhibit C, guaranty, Owner Agreement if the franchisee does not own the hotel, and any residential or mixed-use supplements.

Actor: Applicant, MIF and qualified advisers.

Next dependency: Preserve site control and verify every project date, territory term and signing-window trigger.

5Reach the contractual construction-start milestone

Action: Secure required financing commitments, construction contract, zoning clearances, access rights and building permits; obtain management-company consent; begin the qualifying physical work.

Actor: Franchisee, lender, contractor and government authorities.

Timing: The date appears in the project documents; Item 11 generally allows 15 months after approval.

6Build or convert to approved plans and standards

Action: Follow approved plans, prototype or custom-design review, procurement specifications, Property Improvement Plan for a conversion, electronic-system requirements, signage, furniture, fixtures, equipment and operating-supply standards.

Actor: Franchisee and its architect, contractor and suppliers; MIF reviews for System standards.

Blocker: MIF’s review does not replace code, permit or professional-design responsibility.

7Complete leadership, training and pre-opening readiness

Action: Retain the general manager and sales leadership, use an approved management company when required, complete assigned executive and hotel-opening programs, train required staff and activate Marriott electronic systems.

Actor: Franchisee attendees must complete training to MIF’s satisfaction.

Blocker: Travel, staffing, construction and system-installation dependencies can change the sequence.

8Pass final readiness review and obtain Authority to Open

Action: Finish the hotel, supply required occupancy and accessibility certifications, pass fire/life-safety verification, install systems and inventories, employ trained managers, pay amounts due, maintain insurance and submit a ready notice.

Actor: Franchisee completes; MIF inspects and authorizes.

Blocker: No System Hotel opening before MIF’s signed Authority to Open letter.

Agreement structure

Which SpringHill Suites development path and agreements apply?

The disclosed core arrangement is a franchise for one hotel at one approved location, not an attached area-development program. The Franchise Agreement uses different Exhibit C provisions because a ground-up hotel, a conversion and a change of ownership do not share the same construction or opening conditions.

Official path Governing focus Opening-process distinction
New Development Franchise Agreement plus New Development Exhibit C Construction Start Deadline, Opening Deadline, new-build certifications and Authority to Open.
Conversion Franchise Agreement, Conversion Exhibit C and Property Improvement Plan Renovation, former-brand exit, PIP completion and conversion-specific readiness review.
Change of Ownership Relicensing terms and Change of Ownership Exhibit C Transaction effective date and PIP obligations replace a ground-up construction sequence.
Residential or mixed-use component Additional license, owner or project documents when approved Separate approvals and obligations can sit beside, but do not replace, the hotel franchise documents.
Site approval is not territory protection

Item 12 grants the right to operate one hotel of a stated size at an approved site. Any Restricted Territory is non-exclusive, project-specific, may last less than the full term and may depend on timely development. The applicant must verify the actual boundary, duration and exceptions in the Term Sheet and Franchise Agreement.

Qualification

What must an applicant submit and qualify for?

MIF does not disclose one universal minimum net worth, liquidity amount, credit score, education level or hotel-experience threshold. Its review is project-specific. The official Marriott franchising page describes an appropriate real-estate net worth, entrepreneurial capability and alignment with Marriott values as candidate characteristics; the FDD and application require the evidence used to assess the actual transaction.

Site packageAddress, ownership or lease control, restrictions, plat or site plan, and concept materials for custom or conversion work.
Capital and projectionsDevelopment or conversion budget, financing sources, debt and equity structure, and requested operating projections.
Ownership disclosureEntity chart, controlling parties, owners at the application’s disclosure threshold, and proposed guarantor information.
Management capabilityHotel and management-company experience, operational plan, and a general-manager structure acceptable to MIF.
Due-diligence responsesRequested information about litigation, criminal matters, bankruptcy, foreclosure and professional or gaming-license discipline.
Site control continuityControl must remain effective through contracting; losing the site can make approval ineffective and require a new application.

The new-to-system application fee is due with the application and is generally non-refundable after approval; withdrawal before approval or denial has the limited refund treatment stated in Item 5. That payment is a process trigger, not evidence that the franchise has been awarded. Review the official Marriott franchising process alongside the application and the federal disclosure rule.

Training and staffing

When must leadership, training and support be scheduled?

Training is not one event. MIF assigns programs according to the franchisee’s Marriott experience and operating qualification, while the franchisee must hire required leaders, pay attendee travel and wages, complete electronic-system training, and coordinate instruction with construction and opening readiness.

Pre-opening timing anchors
Lead times are shown against the planned opening or contractual Opening Deadline. They are not additive and do not form a total project duration.
12 months963Opening
Executive OrientationItem 5: at least 12 months; Item 11: at least 6 months
FITM or FOND enrollmentAt least 10 months before the contractual Opening Deadline, when assigned
GM and sales leadershipRetained 6–9 months before opening
6–9 mo.
Pre-opening support windowGenerally 90–120 days before opening
3–4 mo.
Interpretation: the critical scheduling risk is not the length of one class; it is securing the right attendees early enough for assigned programs, staffing, systems installation and the contractual Opening Deadline.

Source: 2026 SpringHill Suites FDD, Items 5 and 11. The 90–120-day period is displayed as approximately three to four months. Executive Orientation contains an internal timing difference that must be confirmed in the issued training schedule.

Buyer verification

Item 5 says new-to-Marriott executives attend Executive Orientation at least 12 months before opening, while Item 11 says at least six months. Treat the earlier 12-month point as the planning target unless MIF confirms in writing which schedule controls for the project and attendees.

Roles and dependencies

Who controls each part of the opening process?

The franchisee owns most execution risk; MIF controls brand approval and opening authorization; lenders, landlords, contractors, suppliers and government authorities control dependencies that MIF does not guarantee. The matrix prevents “assistance” from being read as responsibility for financing, permits or construction.

Phase
Applicant / franchisee
MIF / Marriott
Third parties
Application
Site control, forms, ownership, financing plan
Due diligence and discretionary approval
Advisers, seller or landlord provide transaction evidence
Design and permits
Engage professionals and secure approvals
Review for System standards
Architect, engineer and authorities decide code compliance
Construction
Fund, contract, procure, build and report start
Assess progress and approved-plan compliance
Lender, contractor and suppliers control delivery
Training
Hire attendees and complete assigned programs
Assign, deliver and evaluate training
Management company may operate if consented to
Opening authorization
Certify readiness, insurance, systems and staffing
Inspect and issue Authority to Open
Professionals and authorities issue required certifications

Source: 2026 SpringHill Suites FDD, Items 9, 10, 11, 15 and Franchise Agreement Exhibit C. Marriott generally does not finance or guarantee the project and does not assume the architect’s, contractor’s or authority’s code responsibilities.

Opening authorization

What must be verified before the hotel can open under the brand?

Construction completion alone is insufficient. The New Development and Conversion provisions require a complete readiness package before the hotel may be advertised, promoted or operated as a SpringHill Suites System Hotel.

Approved completionHotel completed to approved plans, System standards and project agreements; architect certification or occupancy evidence if requested.
Accessibility certificationCertification from an appropriately licensed architect, engineer or consultant addressing required accessibility compliance.
Fire and life safetyRequired inspection or approved certification showing fire and life-safety systems are installed and operational.
Systems and assetsFurniture, fixtures, equipment, Marriott electronic systems, fixed-asset supplies and opening inventories installed and working.
Trained managementGeneral manager and department managers employed and successfully trained to MIF’s satisfaction.
Commercial readinessAmounts due paid, required insurance in force, ready notice delivered and opening marketing compliant with standards.

MIF states it will use commercially reasonable efforts to conduct its readiness inspection within 20 days after receiving the ready notice, but it disclaims liability for inability or delay. The final authorization is the signed Authority to Open letter, which establishes the Opening Date and may list remaining work with separate completion dates.

Deadlines

Which deadlines and extension rules can derail opening?

The project’s Construction Start Deadline and Opening Deadline are contract dates, not planning estimates. Missing a required start, completion or opening milestone can create a default even when a lender, permit office, contractor or supplier caused the delay.

Rolling extension The disclosed documents contemplate 30-day automatic extensions in specified circumstances before MIF freezes that mechanism.
Freeze notice MIF may stop further automatic extensions with 60 days’ notice; the restricted-territory period does not automatically extend with the development deadline.
Written extension After construction starts, or after a freeze notice, an additional extension is discretionary, requires a written request and applicable $10,000 fee, and cannot exceed six months under the disclosed provision.
Force majeure limit Qualifying force majeure can support an equitable extension, but the agreement excludes inability to obtain financing from that definition.
Default consequence Item 17 summarizes untimely construction or opening as a curable default with a 30-day cure period, subject to the agreement and applicable state addenda.
Contractual deadline

Do not add the general 15-month construction-start allowance to the 15-month start-to-open expectation and call the result an official 30-month schedule. One is an approval-to-start allowance and the other is an expected build-to-open period; the actual Exhibit A dates, dependencies and approved extensions control.

Buyer verification

What should be confirmed before signing and releasing major capital?

Verify the specific transaction rather than relying on brand-level assumptions. The current FDD, issued Term Sheet, Franchise Agreement, Exhibit C and state addenda should answer each point below; qualified legal, real-estate, lending, design and construction professionals should evaluate their own subject areas.

Correct legal pathNew Development, Conversion or Change of Ownership, plus every owner, guaranty, residential or mixed-use document.
Approval and signing triggerThe exact date approval expires, when any 60-day signing period begins, and what extension is available.
Territory languageActual boundary, duration, exclusions, competing channels and whether timely development conditions the restriction.
Site-control protectionLease or purchase contingencies for franchise approval, permits, financing and design without assuming MIF negotiates them.
Training scheduleRequired attendees, FITM or FOND assignment, Executive Orientation timing and completion standards in writing.
Opening evidenceWho supplies every certification, what the ready notice contains, inspection timing and who signs Authority to Open.
Deadline reliefAutomatic versus discretionary extensions, notice dates, fee trigger, maximum length and effect on territory.
Operator and guarantorApproved management company, equity requirement if imposed, owner agreement, guaranty scope and underwriting evidence.

Use the FTC Franchise Rule resources and 16 CFR 436.2 to distinguish the federal 14-calendar-day disclosure period from Marriott’s application, approval and project deadlines. The rule also gives a separate seven-calendar-day period when the franchisor unilaterally and materially changes attached agreements before signing.

For brand and development context, use Marriott’s official hotel development site, its select-service brand portfolio, and the official SpringHill Suites brand page. Item 20 and the FDD’s current and former franchisee lists are the appropriate starting point for verifying how approval, construction, training and opening authorization worked in actual projects.

Synthesis

What is the practical opening conclusion?

The verified path is a one-hotel, project-specific sequence from FDD receipt and application through MIF approval, executed agreements, site and financing control, construction or conversion, trained management, certified readiness and a signed Authority to Open. The total timeline is undisclosed, not an official 30-month promise. The applicant-controlled dependency is maintaining site, capital, permits, contractors and staffing against the project dates. The decisive franchisor dependency is approval and final opening authorization; the decisive third-party dependency is timely financing, permitting and construction. Before signing, verify the applicable Exhibit C, every deadline, territory condition, training discrepancy and extension trigger.